The major upgrade of the line between Kettering and Corby reaches the next stage in February,
as testing begins on the newly fitted equipment.

Since 2014, work has been taking place to build a second track on the seven-mile stretch between the two Northamptonshire towns as well as installing the associated junctions, signals and foundations for overhead line equipment that will create the potential for a more frequent and reliable service in the future.

The project is a key part of the biggest upgrade of the Midland Main Line since it opened in 1870 and will support better journeys, not just between Northamptonshire and London, but the entire length of the line right through the East Midlands and on to Sheffield.

With much of the infrastructure for the extra line now in place, a nine-day period of testing is required meaning there will be no passenger trains between Corby and Kettering on Saturday 17 February until Sunday 25 February, but there will be a bus replacement service in place.

Cottingham Road bridge in Corby is to close to allow
electrification work to take place on the route to Kettering
.

East Midlands Trains services to all other stations are unaffected and will run as normal.

Spencer Gibbens, Principal Programme Sponsor for Network Rail, said: “A significant amount of work has taken place on the route between Kettering and Corby since this part of the Midland Main Line upgrade began and the project is now approaching the final stages. To safely test the new equipment, our engineers need a nine-day period of ‘wheels free’ access to the railway, meaning a short period of bus replacements between Kettering and Corby is unavoidable. From 2020, when the upgrade of the Midland Main Line is complete, passengers will really see the benefits of this investment and I’m grateful for their patience while the work is carried out.”

Jake Kelly, Managing Director, East Midlands Trains, said: “The final testing of this seven-mile stretch of track is an important milestone for the upgrade of the Midland Main Line. Although the main benefits of this work will arrive in 2020, it will help to maintain a reliable service for our customers today, including providing a new diversion route if the main line to London is disrupted.  While this work is being carried out, we will be providing a bus replacement service between the two stations as well as ensuring staff are on hand at both stations to help customers. Passengers should check with eastmidlandstrains.co.uk for details about the journey between Kettering and Corby during this time.”

So far the Kettering to Corby route has seen:

  • Fourteen bridges and viaducts strengthened – including Harpers Brook Viaduct, a 12 arch brick structure constructed in 1879
  • 21 kilometres of track laid (12km of new track and 9km renewal of exiting track)
  • 4km of drainage equipment installed
  • 15km of railway embankment stabilisation completed
  • 73km of signal and power cabling laid
  • Six new signal gantries erected
    The creation of a wider ‘gauge’ – meaning larger freight containers can be transported on the route.

For all enquiries, contact:

Network Rail press office – Toby Higgins
toby.higgins@networkrail.co.uk
Network Rail
01904 383180 / 07850 406724

Click on the .pdf link below, for an A5 booklet:
A5 Booklet Network Rail

About Network Rail Network Rail owns, manages and develops Britain’s railway – the 20,000 miles of track, 40,000 bridges and viaducts and the thousands of signals, level crossings and stations (the largest of which we also run). In partnership with train operators we help people take more than 1.65bn journeys by rail every year and move hundreds of millions of tonnes of freight, saving almost 8m lorry journeys. We employ 38,000 people across Britain and work round-the-clock, each and every day, to provide a safe, reliable railway.

About the Railway Upgrade Plan The Railway Upgrade Plan is Network Rail’s investment plan for Britain’s railways. It makes up two-thirds of Network Rail’s £40bn spending priorities for the five years to 2019 and represents the biggest sustained programme of rail modernisation since the Victoria era. It is designed to provide more capacity, relieve crowding and respond to the tremendous growth Britain’s railways continue to experience; passenger numbers have doubled in the past 20 years and are set to double again over the next 25 years – so we need to continue to invest in building a bigger, better railway. For passengers, that means:

  • longer, faster more frequent trains;
  • better, more reliable infrastructure; and
  • better facilities for passengers, especially at stations.

Follow us on Twitter: @networkrail Visit our online newsroom: www.networkrailmediacentre.co.uk

Leave a Reply

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <s> <strike> <strong>